For me, she resembles a mother.
December 8, 2015 in addis abeba (fbc) in keeping with an declaration from ethiopian electric electricity, 9
December 8, 2015 in addis abeba (fbc) in keeping with an declaration from ethiopian electric electricity, 90% of the protection at the 132 kv high-energy transmission line from abi addi to adwa has been finished. Tesfaye mengete, the manager of the institution’s excessive strength transmission traces upkeep
and technical workplace, stated that tomorrow’s test work can be performed to confirm that the adwa and axum substations receive energy due to the fact the preservation of the energy transmission line has basically been completed. Additionally, the ethiopian energy carrier restored and completed the 66 kv
transmission line from the adwa-shire substation; however, a fault with the breaker turned into discovered all through the test paintings to offer strength from the shire substation. In line with the facts we acquired from ethiopian power, the locations that get hold of strength from the line would be able to get hold of energy via solving the breaker failure.